Built for the people actually running the shift, checking in, capturing photos, validating APs, logging cables, and keeping Phil and Wayne ahead of surprises.
| Location | Required shots | Status |
|---|---|---|
| GDC | Closed, open, interior, extra angles | Pending |
| GM | Closed, open, interior, extra angles | Pending |
| GRC | Closed, open, interior, extra angles | Pending |
| PICS | Closed, open, interior, extra angles | Pending |
| TLE | Closed, open, interior, extra angles | Pending |
| UPC | Closed, open, interior, extra angles | Pending |
| RCV01 / RCV02 | Closed, open, interior, extra angles | Pending |
| RX | Closed, open, interior, extra angles | Pending |
| Rear EDC | Closed, open, interior, extra angles | Pending |
| Item | What to check |
|---|---|
| AP018, AP019, AP511, AP512 | Correct new locations, mounting readiness, field match to AP map |
| AP229, AP809 | Correct moved locations, no stale assumptions from old placement |
| Ping sweep vs worksheet | Closets / switches that appear in worksheet but not clearly in baseline must be reconciled early |
| Port worksheet | Every touched cable must end up with correct switch / port documentation |